On a recent weekday afternoon, men in
hard hats and neon safety
vests climbed up and
down ladders just outside the arrival doors at the Albuquerque International
Sunport.
Work crews are a now-familiar presence
at the state's largest airport – and travelers may see more of the same for the
next few months as the facility's "Terminal Improvement Project"
approaches the three-year mark.
Airport officials say the installation
of lights is the last remaining piece of a facility update that former Mayor
Richard Berry said would put "the best possible face on Albuquerque we
can."
The contractor, Flintco, has until the
end of February to finish the job – that’s according to the 20th change order
approved for a project that is now 1½ years behind schedule and about $2.5
million over the initial budget.
Albuquerque aviation director Nyika
Allen blames the delays in part on inadequate project "scoping" –
which she says is the purview of the city and the architect – and problems with
Flintco's electrical subcontractor. But she said the Sunport has the
wherewithal to cover the price increase and that the work has had little effect
on the traveling public.
"No one likes to see the ceiling
open, that’s for sure,” she said in a recent interview. "But otherwise we've
been 100% open."
The work started in early 2017. The
objective was to "refurbish and upgrade the ticketing, baggage claim and
exterior areas of the terminal," according to a Feb. 24, 2017, Sunport
news release. It was to take 15 months and cost $30 million.
But construction time has since more
than doubled and the cost has risen to $32.4 million.
Allen said the city bears some
responsibility since it should have anticipated at least a few of the changes
ultimately built into the project.
The first change order, for example,
was requested in May 2017, less than two months into the job. It totaled more
than $900,000 and pertained primarily to the facility's stucco.
Renovation plans included new, larger
windows on the arrivals level, which would require some stuccoing around them.
But the project architect told the city in a memo that it was "next to
impossible" to match new stucco surrounding windows to the rest of the
facade, which was already inconsistent due to age, damage and previous patch
repairs. Also, crews found "extensive unanticipated water and rust damage
to the existing structural studs and stucco finish associated with the portico
columns" on the second level.
The city ultimately approved stuccoing
the entire north facade and portico entrances.
Though Allen did not take over the
Sunport until 2018 – as an appointee of Mayor Tim Keller – she cited the stucco
as a significant issue that should have been addressed during the project's
scoping phase.
"You can't just patch stucco in a
tiny spot; you need to do the stucco on that side," she said. "I don't
know why that wasn't thought about."
But changes to the scope of work was
not the only problem.
Flintco’s electrical contractor
"essentially walked off the job" and had to be replaced, Allen said.
And the electrical contractor left
problems in its wake.
In seeking one of its timetable
extensions, Flintco's Rebecca Masters said some of the original electrical
contractor's work had to be redone. She blamed the company for "disordered
materials and unsatisfactory work that requires extensive reinstallation or
reordering of lighting fixtures and accessories," according to an Aug. 9,
2019, memo to the project's architects obtained by the Journal through a public
records request.
A Flintco representative acknowledged
that replacing the original electrical contractor created delays but said the
project also included "unforeseen conditions" and work beyond the
original outline.
"Throughout the project, Flintco
has remained flexible and responsive in accommodating the operational
requirements of the airport and the traveling public. The vast majority of the
project has been completed and remains open," Steve Eikanger, Flintco vice
president and area manager, said in an email, adding that the company was
currently waiting for delivery of the last set of decorative light fixtures.
"This important infrastructure project is slated for completion early next
year (2020) and will deliver an exceptional result to the City of
Albuquerque."
Allen said the airport has not decided
whether to pursue any penalties against Flintco, saying she would evaluate the
options once the project is finally finished. In a push for completion, Allen
said she had Flintco personnel establish an on-site office and meet weekly with
the Sunport staff.
"I think there were a lot of unforeseen
circumstances that also had to deal with, (but the contractor's performance)
wasn't great," she said. "I think they are working with us now, but I
think we should expect a lot from people who are doing public projects and the
bar should be set high for these contractors."
Allen said the Sunport has the
self-generated revenue to cover the project. Half comes from a capital fund
that airlines pay into, and a half from passenger facility charges, she said.
没有评论:
发表评论